In September 2014, Allana Agnew provided readers with an update in relation to the amended QBCC Act. (Click here to view our September Update).
According to the Minister for Housing and Public Works, “…the amendments are intended to reduce red tape and create fair regulation so that the industry has the best possible platform for…growth”.
Below is our summary of the TOP 10 amendments to the QBCC Act.
1. LICENSING AND FINANCIAL REPORTING REQUIREMENTS
Licensees will have the opportunity to renew their licence ever three years as opposed to 12 months and they will no longer be required to provide financial reports to the QBCC when renewing their licences.
2. REDUCED STATUTORY WARRANTY FOR NON STRUCTURAL DEFECTS
The time period for Statutory Warranties in relation to non structural defects had been increased from 7 months to 1 year.
3. CONSISTENT DEFINITION OF “PRACTICAL COMPLETION”
The definition of practical completion for domestic building contracts has been changed so there is one consistent definition for both Level 1 and Level 2 contracts. “Practical Completion” for a domestic building contract is now defined as:
“…the day when the subject work is completed – in compliance with the contract, including all plans and specifications for the work and all statutory requirements applying to the work; and
(a) without any defects or omissions, other than minor defects or minor omissions that will not unreasonably affect occupation; and
(b) if the building owner claims there are minor defects or minor omissions – the building contractor gives the building owner a defects document for the minor defects or minor omissions.”
4. VARIATION THRESHOLDS FOR INSURANCE PREMIUMS
If residential (or speculative residential) construction work carried out under a contract is to be varied, then the value of the residential construction work must increase by at least $5,000 or more because of the variation before any additional insurance premium is payable.
5. CLAIMS FOR EXTENSION OF TIME
There is now an obligation on building contractors to notify the consumer within 10 business days of becoming aware of the “cause and extent” of any delay when claiming for an extension of time.
6. NO SIGNATURE REQUIRED FOR ANY CLAIM FOR EXTENSION OF TIME
Any request for an extension of time by a building contractor under a regulated contract must be approved “in writing” by the building owner. The approval does not need to be signed by the building owner. “Writing” also includes electronic communications.
7. BREACH OF WARRANTY PROCEEDINGS
In proceedings for a breach of warranty under a regulated contract, it is now a defence for the builder to prove they were not reasonably given access to the property to rectify any alleged deficiency. For completion, it is also a defence for the builder to prove the deficiencies arose from instructions given by the person for whom the work was done, contrary to written advice of the builder.
8. PROTECTION FOR NEIGHBOURS
The amendments provide greater protection for building owners impacted by works being done on an adjacent property. Contractors will be liable to remedy damage to a neighbouring property, not just any damage incurred on the site on which they are working. The owner or occupier of a residential property adjacent to a building site may request the QBCC to give a direction to remedy any consequential damage to their property.
9. DISCIPLINARY PROCEEDINGS
The amendments introduce a new, free, faster and more consistent process under which the QBCC will deal with all building disciplinary proceedings. Building disciplinary matters are currently dealt with by QCAT, which can be lengthy and costly for licensees. If a decision is made by the QBCC and a licensee wants the decision reviewed, then they can apply for an internal review of the decision through the QBCC or alternatively they can appeal to QCAT. The QBCC Act also extends the grounds for disciplinary action to include the failure of a contractor to pay a subcontractor in accordance with their contract.
10. DOMESTIC BUILDING CONTRACTS
The amended QBCC Act introduces Schedule 1B titled “Domestic building contracts” and repeals the Domestic Building Contracts Act 2000 (Qld). The amended QBCC Act imposes different requirements for Level 1 and Level 2 regulated contracts and outlines the minimum requirements for both. To be valid, both level regulated contracts must be in written form, dated and signed by each of the parties. The difference between the 2 levels can be summarised as follows:
- LEVEL 1 REGULATED CONTRACTS are domestic building contracts, cost plus contracts or mixed purpose contracts for which the contract price, amount payable for contracted services or amount referable to the contracted services (respectively) is more than the regulated amount ($3,300 or higher, if prescribed in Regulations) but less than the level 2 amount.
- LEVEL 2 REGULATED CONTRACTS are domestic building contracts, cost plus contracts or mixed purpose contracts for which the contract price, amount payable for contracted services or amount referable to the contracted services (respectively) is equal to or more than the level 2 amount.
The Level 2 Amount (or threshold) will be prescribed by amended Regulations. Unfortunately, those draft regulations have not yet been published. We will issue a further Alert with an update on the effect of the published Regulations, when available.